2026-11-10·Panjin · Liaoning · China
First test of crude intake at HAPCO's Panjin refinery
On 10 November 2026 Sentinel-2 caught a plume rising over the process area of HAPCO's new 300,000 b/d refinery at Panjin, in China's Liaoning province. It is the first in seven clear passes since 1 October. It comes a month after the first Arabian crude cargo reached the plant and four weeks after its crude unit was declared mechanically complete. We read it as the first test of crude intake.
HAPCO's refinery at Panjin on Sentinel-2, 10 November 2026. The box marks the plume over the process area; circles mark tanks T09 and T10, the two crude tanks that have filled. The dark arc just north of each tank is its shadow on the ground. Contains modified Copernicus Sentinel data 2026.
A plume over the process area on 10 November
HAPCO (Huajin Aramco Petrochemical Company, 华锦阿美石化) is building a 300,000 b/d refinery, a 1.65 million t/y ethylene cracker and a 2 million t/y paraxylene plant at Panjin, on the Liaodong Gulf. North Huajin holds 51 %, Aramco 30 % and Panjin Xincheng 19 %. Aramco has committed to supply up to 210,000 b/d of crude.
On the morning of 10 November a white plume rises from a block of fired heaters in the middle of the process area, about 2 kilometres south-west of the crude tanks, and casts its shadow to the north-north-west. None of the seven clear Sentinel-2 passes between 1 October and 6 November shows anything there.
The plume block at HAPCO on Sentinel-2, 6 and 10 November 2026, 950 m across. On 10 November a white plume sits in the box; the dark streak running north from it is its shadow. Contains modified Copernicus Sentinel data 2026.
We read it as the first test of crude intake. The crude unit was declared mechanically complete on 12 October, the first Arabian cargo arrived on 9 October, and crude has started to leave one of the tanks.
From first cargo to first plume
| Date | Event | Seen by |
|---|---|---|
| Oct 2025 | Twelve 1.1 Mbbl floating-roof crude tanks finished; their levels hold steady for ten months. | Sentinel-1 |
| 16 Aug – 9 Sep 2026 | T09 starts filling, from 25 % to 59 %. | Sentinel-1 |
| 30 Sep | 2.5 Mt/y hydrocracker mechanically complete; 14 of 32 units done. | HAPCO |
| 9 Oct | First Arabian crude cargo arrives. | HAPCO, Aramco |
| 9 – 17 Oct | T10 fills from 3 % to 53 %, about 0.55 Mbbl. | Sentinel-2 |
| 12 Oct | 15 Mt/y crude and vacuum unit and 4.2 Mt/y cracking unit mechanically complete; 21 units done. | HAPCO |
| 15 Oct | Last Sentinel-1 image of the site; none acquired over the Liaodong Gulf since. | ESA catalogue |
| 22 Oct – 3 Nov | T09 falls from about 80 % to 57 %, about 0.2 Mbbl. | Sentinel-2 |
| 30 Oct | 5 Mt/y residue desulphurisation and butadiene units complete; 23 of 32 units, 88 % built. | HAPCO |
| 10 Nov | First plume over the process area. | Sentinel-2 |
Two of twelve crude tanks have filled
Twelve floating-roof tanks of 1.1 million barrels each, about 13 million barrels in all, stand north-east of the process area. They were finished in October 2025 and held a steady low level until August. Two have taken crude since: T09 from mid-August, and T10 in the week the first Arabian cargo arrived, about 1.1 million barrels together. Since 22 October T09 has given back about 0.2 million barrels. The other ten are still at their floor.
Sentinel-1 has not imaged the Liaodong Gulf since 15 October, so the radar series stops there; roof shadows on Sentinel-2 carry the tanks to 10 November. The two methods place idle tanks at different levels, about 20 % on radar and 5 % in shadows, so compare changes between them rather than levels.
Imagery: contains modified Copernicus Sentinel-1 and Sentinel-2 data 2025–2026.
Sources: Hydrocarbon Engineering, 15 October 2026 (first Arabian crude, ownership) · Aramco, March 2023 (capacity, crude supply) · HAPCO project announcements of 30 September, 12 October and 30 October 2026 (mechanical completion).