2026-11-17·Daqing · Heilongjiang · China
Daqing's 48 new crude tanks have held water, not oil
Beside the crude terminal at Daqing, in Heilongjiang, two blocks of 24 floating-roof tanks went up in 2025 and 2026: 48 tanks, about 47 million barrels of space by our measure. From orbit, their roofs rose near the top and came back down one tank after another. A tank being filled with crude does not empty again three weeks later. A tank being tested with water does. On 3 November all 48 read empty.
Point at the chart to read a day
The south block was tested in November and December 2025, with the air at −5.6 °C on average and down to −21.8 °C at night; the north block from April to mid-August 2026, at 17.9 °C. China's tank construction code, GB 50128, asks for test water at 5 °C or warmer and allows another liquid with approval. The radar reads the roof, not what lifted it, so the south block's test liquid is not known.
Two blocks, tested one tank at a time
The south block's walls went up in September and October 2025. From 1 November to 7 December, 22 of its 24 tanks read near full in turn, each for a few weeks, then empty. Roof shadows on Sentinel-2 show the same sequence. The north block, built from January to April 2026, followed from April to mid-August: all 24 tanks, a median peak of 89%, about 18 days near the top each.
From late May to late July the new tanks held between 3.4 and 5.3 million barrels in total while the full tanks kept changing. The same volume moved from tank to tank, which is how a water test runs. Four south tanks went up in 2026 as well; the last two drained between 15 and 27 October, and Sentinel-2 shows empty-roof shadows on 27 October.
The radar reads the height of the roof, not what lies under it. The water is an inference from the pattern. It fits 46 of the 48 tanks; the other two never moved.
The earlier farms point to mid-2027 and early 2028
We found the same sequence, a water test then a wait, at 12 Chinese tank farms built since 2017. The wait from test to first crude ran from 8 to 43 months, 19 at the median.
Counted from the end of each block's tests, that median puts first crude in the south block around July 2027, and in the north block around March 2028. The middle half of the earlier farms gives a window from now to January 2028 for the south block, and from July 2027 to September 2028 for the north. Twelve farms is a small sample, not all of them are state reserves, and the timing of a first fill depends on prices and policy as much as on construction. We will report the first sustained rise when it shows.